MRT3 Circle Line in 2026: Land Acquisition, Compensation and What KL Owners Near the Route Should Know Before 2032

The 51km loop has its final railway scheme, 690 lots are being acquired, and opening is targeted for 2032. Here is what is confirmed, what is still interim, how compensation works under the Land Acquisition Act 1960, and a checklist for owners and buyers near the route.

Also on Medium: read it on Medium

Illustration of a generic circular elevated rail loop with a gold four-car train running around terraced houses, with a generic skyline of flat-roofed blocks behind and a survey map, magnifying glass, stamped document, measuring tape and keys on a desk in the foreground

The MRT3 Circle Line is the last big piece of the Klang Valley rail network still on paper. It is planned as a loop of about 51km around the edge of Kuala Lumpur, linking the existing MRT, LRT, KTM and Monorail lines. It is not yet under construction. What is happening now is quieter but matters more to some owners: land is being acquired.

If you own a home, a shop or land near the planned route, or you are thinking of buying there, you will hear two kinds of talk. One is hopeful: “MRT coming, prices will go up”. The other is anxious: “Is my lot affected? What will I be paid?” This article sets out what the official sources actually say as at 4 November 2026:

  • What is confirmed, from MRT Corp’s own statements and the Transport Minister’s written reply to Parliament.
  • What is still interim, including station names and the cost.
  • How land acquisition and compensation work, from the text of the Land Acquisition Act 1960.
  • Practical checklists for owners whose lots are affected, for owners next to the route, and for buyers.

The short answer: the line has its approvals, acquisition is under way, and construction is expected from 2027. No official figure measures a “station premium” for property near the future stations, and this article does not claim one.

Not advice. This is general information from MRT Corp, the Ministry of Transport, a written parliamentary reply, the Land Acquisition Act 1960 and news reports, as at 4 November 2026. Land acquisition law is technical, and every lot is different. If your land is affected, please speak to your own lawyer and an independent registered valuer before you accept or object to any award.

The line in brief

  • What it is: an orbital line of about 51km around the perimeter of Kuala Lumpur, with 10 interchange and connecting stations to existing lines (MRT Corp, 17 July 2025).
  • Approval: the Transport Minister approved and signed the Final Railway Scheme on 17 July 2025.
  • Land: the number of land lots to be acquired was cut from 1,012 to 690 after public feedback.
  • Acquisition: under way, with completion targeted for the end of 2026 (MRT Corp).
  • Construction: physical construction is expected to begin in 2027 (Transport Minister, July 2026).
  • Opening: the line is scheduled to be operational by 2032 (Transport Minister, July 2026).
  • Interchanges, per MRT Corp’s project page: two with the MRT Kajang Line, two with the MRT Putrajaya Line, two with the LRT Kelana Jaya Line, two with the LRT Ampang Line, one with the Monorail, two with KTM Komuter and one with a city bus station.
  • Cost: no updated official cost has been published (see below).

A note on the numbers. MRT Corp’s statements say the line is 51km. Its project page gives 50.8km, with 31 stations (24 elevated and 7 underground) and 15 park-and-ride sites with 11,650 bays. The same page still shows older opening dates (“Phase 1 in 2028, Phase 2 in 2030”), which the government has since replaced with a 2032 target. So treat the station count and parking figures on that page as subject to change too.

What has happened so far

Timeline of the MRT3 Circle Line from the public inspection of 2 September to 2 December 2024, the section 8 gazettes of 15 July 2025 for Selangor and 15 August 2025 for Kuala Lumpur, the Final Railway Scheme approval on 17 July 2025, MRT Corp’s land protection notices in June 2026, the minister’s reply in July 2026 and the UM agreement on 21 October 2026, to the targets of end-2026 for land acquisition, 2027 for construction and 2032 for operation
MRT3 Circle Line milestones and official targets. Sources: MRT Corp media releases (30 August 2024, 17 July 2025); Transport Minister’s written parliamentary reply, reported by Media Selangor, 17 July 2026; MRT Corp notices, June 2026; The Malaysian Reserve and Utusan Malaysia, 21–22 October 2026.

1. Public inspection, 2 September to 2 December 2024. MRT Corp put the proposed alignment, site plans and project details on public display for three months, at 35 locations and online. MRT Corp said the exercise was held in accordance with section 84 of the Land Public Transport Act 2010.

2. Section 8 gazettes, July and August 2025. The Transport Minister, Anthony Loke, said in a written parliamentary reply in July 2026 that the land for the project was gazetted under section 8 of the Land Acquisition Act 1960 on 15 July 2025 for Selangor and 15 August 2025 for Kuala Lumpur. Section 8 is the formal declaration that the listed land is needed. More on what that means below.

3. Final Railway Scheme approved, 17 July 2025. MRT Corp said it received more than 45,000 written responses during the public inspection, and 93.3% expressed support. It said it changed the placement of stations and viaducts and the design of the rail system, and that this cut the number of lots to be acquired from 1,012 to 690. That is 322 fewer lots, or about 32% (my calculation). MRT Corp said it would contact affected communities about the changes in their areas.

4. Other approvals. In the same parliamentary reply, the minister said the environmental impact assessment (EIA), social impact assessment (SIA) and heritage impact assessment (HIA) had been approved. He said the work so far was “limited to the land acquisition stage”.

5. Getting ready to hold the land, June 2026. On 29 June 2026, MRT Corp invited expressions of interest from contractors for “protection of land along MRT3 Circle Line”, covering demolition, fencing and hoarding, site clearing, signage and locked gates, and for routine maintenance works within land along the line. These are not the main construction contracts, but they show MRT Corp preparing to secure land it takes over.

6. Tracing owners. In October 2025, MRT Corp posted public notices asking the registered owners and next of kin of two lots in Segambut Dalam, Kuala Lumpur, to contact it. If a lot is still registered to someone who has died, the family may need to sort out the estate before compensation can be paid to the right people.

7. A proposed station at Universiti Malaya, 21 October 2026. At Transport Expo Asia 2026, MRT Corp and Universiti Malaya exchanged an agreement on a proposed underground station within the UM campus, provisionally named “Stesen UM”, in the UM Health Zone, which includes Universiti Malaya Medical Centre (UMMC) and Universiti Malaya Specialist Centre (UMSC). The Malaysian Reserve reported that it is expected to improve connectivity for communities including Bangsar South and Pantai Dalam, with a link to the LRT Kelana Jaya Line via Universiti station and a planned interchange with the MRT Kajang Line. Utusan Malaysia reported that the agreement was made through MRT Corp’s project company, MRT Lingkaran Sdn Bhd. This is a proposal, and the name is provisional.

What is still not settled

  • Station names and exact positions. The 2024 public inspection plans included stations at places such as Sri Hartamas and Dutamas, The Star reported at the time. MRT Corp then changed the placement of some stations and viaducts in the final scheme. I have not found a final, official station list published by MRT Corp since the approval. Treat any station name, including Stesen UM, as provisional.
  • The cost. In the revised Budget 2023 in February 2023, the government said it would review the cost, aiming to bring it below RM45 billion from an estimated RM68 billion in 2018, The Star reported. No updated official cost has been announced since.
  • Construction contracts. No main construction contract for the line has been announced. Some websites carry old reports about MRT3 tenders from 2017 and 2018 that now show a recent date; they describe an earlier, mostly underground design and are out of date.
  • Budget 2027. Budget 2027, tabled in October 2026, did not include an MRT3 announcement, The Edge reported.
  • Whether the end-2026 target will be met. Acquisition is under way, but no official figure has been published on how many of the 690 lots have been awarded or taken over.

Which areas are involved

The line is designed to serve the outer ring of Kuala Lumpur and parts of Selangor, including areas under the Ampang Jaya Municipal Council (MPAJ), which MRT Corp listed among the agencies it worked with on the alignment. Based on the interim station names shown in 2024 and later reports, the loop passes areas such as Sri Hartamas, Dutamas, Segambut, Titiwangsa, Setapak, Setiawangsa, Ampang, Pandan, Cheras, Salak Selatan, Kuchai, Old Klang Road, Pantai Dalam, Bangsar South and the UM area.

That list is a guide, not a map. Whether a particular lot, row of shops or building is affected depends on the gazetted schedule of lands, not on a station name. The way to check is in the checklist below.

Why MRT Corp cut the lots from 1,012 to 690

Bar chart showing the number of land lots to be acquired for the MRT3 Circle Line falling from 1,012 under the proposed alignment at the 2024 public inspection to 690 under the Final Railway Scheme approved on 17 July 2025, a reduction of 322 lots or about 32%
Land lots to be acquired for the MRT3 Circle Line. Source: MRT Corp media release, 17 July 2025. Difference and percentage are the author’s calculations.

MRT Corp said the cut came from feedback during the public inspection, with changes to where stations and viaducts sit and to the design of the rail system, and that it was meant to minimise the impact on affected communities. It also said it worked on the alignment with agencies including the Land Public Transport Agency (APAD), Kuala Lumpur City Hall (DBKL), MPAJ, the Selangor state economic planning unit (UPEN Selangor), the Public Works Department (JKR) and the Drainage and Irrigation Department (JPS).

The practical point: if you were told in 2024 that your lot was on the proposed alignment, do not assume it still is, or that it no longer is. The lots that count are the ones in the schedule to the section 8 declaration.

How land acquisition works: the steps in the Act

Compulsory acquisition in Peninsular Malaysia is governed by the Land Acquisition Act 1960 (Act 486). The steps below are from the text of the Act. It was amended in 2016, so check the current text, and your lawyer, for the details that apply to you.

  1. Preliminary notice (section 4, Form A). The State may gazette a notice that land in a locality is likely to be needed. Officers may then enter and survey (section 5, Form B). They must show their authority, and may not enter a building or enclosed garden without consent or three days’ written notice.
  2. Declaration (section 8, Form D). The State gazettes a declaration that the listed land is needed, with a schedule of the lands. The declaration is conclusive evidence that the scheduled land is needed. For MRT3, this happened on 15 July 2025 (Selangor) and 15 August 2025 (Kuala Lumpur).
  3. Note on the title (section 9). The Land Administrator marks out the affected area and makes a note of the intended acquisition on the register document of title. Under the 2016 amendment, for strata property the note also goes on the strata register.
  4. Planning information (section 9A). The Land Administrator asks the planning authority for the land use shown in the development plan for the land. In Kuala Lumpur, that information comes from the Commissioner of the City of Kuala Lumpur. It is then used in valuing the land.
  5. Notice of enquiry (sections 10 and 11, Form E). The Land Administrator gives public notice and fixes a date for an enquiry into claims for compensation. The enquiry cannot be held earlier than 21 days after the notice. Copies are served on the occupier, the registered owner, anyone with a registered interest (such as a bank holding a charge or a registered lessee) and anyone else believed to have an interest. A Form F notice may also ask the owner for information in writing.
  6. The enquiry (section 12). The Land Administrator enquires into the value of the land, who has an interest in it, and any objection to the area being taken, and then assesses compensation under the First Schedule. The Land Administrator may get a written valuation opinion from a valuer first. Small or many-owner cases can go through a summary enquiry (section 17).
  7. The award (section 14, Form G) and notice of award (section 16, Form H). The Land Administrator makes a written award for each person whose interest is established, and serves each of them a Form H with an extract of the award.
  8. Payment (section 29). After Form H is served, the Land Administrator pays each amount awarded. If the person does not consent to receive it, or there is a dispute over title or how the money is split, the money is paid into court instead. If payment is late, the Act provides for late payment charges (section 32).
  9. Possession (sections 18 and 22, Form K). The land can be taken from when Form H is served on the occupier, or later. Formal possession is taken by serving or posting a Form K. The title is then endorsed to show the land has vested in the State, or that the specified part has been acquired (section 23). Where only part of a lot is taken, the rest is resurveyed, the rent (cukai tanah) is revised and a title in continuation is issued (sections 25 and 26).

Two more provisions worth knowing:

  • The two-year limit. Under section 8(4), a declaration lapses for any land for which the Land Administrator has not made an award within two years of the gazette. On the dates the minister gave, that is 15 July 2027 for the Selangor land and 15 August 2027 for the Kuala Lumpur land (my calculation), unless an award has been made by then. This does not apply where possession was taken under a certificate of urgency (section 19A, added in 2016). Ask your lawyer how this applies to your lot.
  • Urgent possession (sections 19 and 20). In urgent cases, the State can issue a certificate of urgency and take possession before an award. Where there is a building, the occupier is given a Form J notice to vacate within a period of up to 60 days, with an offer of compensation for the building. I have seen no report of this being used for MRT3.

How compensation is worked out

The First Schedule of the Act sets the rules. In plain terms:

The starting point is market value at a fixed date. That date is the date of the section 4 notice, if a section 8 declaration followed within 12 months, or otherwise the date of the section 8 declaration. For MRT3 land, the section 8 dates are 15 July 2025 (Selangor) and 15 August 2025 (Kuala Lumpur).

How market value is assessed:

  • The valuer may use any suitable method, with regard to recent sales of similar land nearby, and particular consideration of the last transaction on the lot itself within two years before the valuation date.
  • Sales after the valuation date are ignored. A rise in nearby prices in 2026 does not count.
  • If only part of a lot is taken, it is valued by reference to the whole lot as shown on the title, with regard to the features of the part taken.
  • For leasehold land, the remaining years on the lease can be taken into account.
  • The planned land use in the development plan, from section 9A, is taken into account.
  • Restrictions in the title, such as a category of land use or an express condition, are taken into account.

What else is added:

  • Severance: damage from separating the acquired part from the rest of your land.
  • Injurious affection: damage to your other property caused by the acquisition.
  • Reasonable expenses of moving your home or business if you are forced to move.
  • Where only part of a lot is taken, any clear and enforceable undertaking to build roads, drains, walls or fences for the part you keep.

What is deducted: any increase in the value of your other land that is likely to come from the use the acquired land will be put to. In other words, if the remaining part of your lot gains from being next to a station, that gain can be set off against your compensation.

What is ignored:

  • Any increase in value from the project itself. The value of the acquired land “likely to accrue from the use to which it will be put” does not count. There is no “MRT premium” in an acquisition award.
  • Any fall in value from the use it will be put to.
  • Your unwillingness to sell, and the urgency of the acquisition.
  • Improvements made after the section 8 declaration, other than repairs needed to keep a building in proper condition. Improvements made in the two years before the declaration are also disregarded, unless shown to be made in good faith and not in anticipation of the acquisition.
  • Increases from unlawful use. A building not permitted by the land’s category of use or the title conditions is disregarded.

One rule that catches people out (First Schedule, paragraph 4): if you state a value or claim an amount at the enquiry, you cannot later be awarded more than you claimed. If you fail to make a claim without good reason, you cannot later be awarded more than the Land Administrator’s award. So make a full claim, on time, and back it up.

If you disagree with the award

  • Who can object (section 37). A person with an interest who made a claim at the enquiry in time and did not accept the award, or accepted payment under protest as to the amount, can object to the measurement of the land, the amount of compensation, who it is paid to, or how it is split. Very small awards below a statutory threshold cannot be challenged on amount.
  • How (section 38, Form N). By a written application in Form N to the Land Administrator, asking for the matter to be referred to the High Court. State all your grounds. Other grounds cannot be argued in court without leave.
  • When (section 38(3)). If you were present or represented when the award was made: within six weeks of the award. Otherwise: within six weeks of receiving Form H or six months from the award, whichever ends first. The court can extend these only in special circumstances.
  • Deposit (section 39). You will be asked to deposit RM3,000 or 10% of the amount claimed, whichever is less, as security for costs. If it is not paid within 30 days, the application is treated as withdrawn and the award becomes final.
  • The acquiring party can object too. For larger awards, the body the land is acquired for can also object (section 37(3)). The Act lets the Land Administrator withhold 25% of a larger award while that body’s six-week window to object is open and, if it objects, until the court decides (section 29A).

The practical point: accept under protest, in writing, if you want to take the money and still object, and diarise the six-week deadline from the day of the award.

What the public said

Donut chart showing that 93.3% of more than 45,000 written responses to the MRT3 Circle Line public inspection from 2 September to 2 December 2024 expressed support for the project
Written feedback to the MRT3 public inspection, 2 September to 2 December 2024. Source: MRT Corp media releases, 30 August 2024 and 17 July 2025. “Other responses” is the author’s calculation.

MRT Corp received more than 45,000 written responses, and 93.3% supported the project. It did not publish a breakdown of the rest. Broad support for a line is not the same as agreement on what each owner is paid, which is why the objection process above matters.

Is there an “MRT3 premium” near future stations?

You may hear that homes near a future MRT3 station will rise by a fixed percentage. No official source measures this.

  • NAPIC does not publish prices by distance to a station. Its house price index is by state and district, and there is no MRT3 station to measure from yet.
  • The line is years away. Construction is expected from 2027 and opening by 2032. Between now and then, the area around a future station may see years of construction traffic, noise and diversions.
  • Station positions are not final. A home “near the future station” may turn out to be further away, or next to a viaduct or ventilation shaft rather than an entrance.
  • The law ignores it for acquired land. As above, compensation disregards any increase in value from the project itself.

The nearest thing to an official comment is general. In its Property Market Report for the first half of 2026, NAPIC noted upward rental trends in some high-demand areas of Kuala Lumpur, “particularly those adjacent to LRT and MRT stations”. It gave no figure, and it was talking about stations that already run.

So if anyone quotes you an “MRT3 premium” for a property near the route, ask where the number comes from. If it is not based on recent transactions of comparable units, treat it as a sales line, not data. A bank valuer will look at comparable transactions, not at a line on a map.

Checklist: if your lot may be affected

  1. Check whether your lot is scheduled. Ask the Land Administrator: the district land office (Pejabat Tanah) in Selangor, or the Federal Territory Land and Mines Office (PTGWP) in Kuala Lumpur. Give your lot number, mukim and title number, and ask whether it is in the schedule to the section 8 declaration and whether the area taken is the whole lot or a part. You can also call MRTCareline on 1800-88-6782.
  2. Do a title search. A note of intended acquisition under section 9 should appear on the register document of title, or on the strata register for a strata unit.
  3. Read every notice carefully, and keep it. Form E (enquiry), Form F (request for information), Form H (award) and Form K (possession) each start a clock or a step. Note the date you received each one.
  4. Attend the enquiry, or send your lawyer. This is where your claim is heard. If you are not present or represented, the deadlines for objecting change.
  5. Make a full written claim. Include the land, any building, severance and injurious affection if only part of your lot is taken, and moving costs for your home or business. You cannot later be awarded more than you claimed.
  6. Get your own valuation. Ask an independent registered valuer for a report on market value at the section 8 date, using comparable sales up to that date. Keep your own records of what you paid, renovations with permits and receipts, and rental income.
  7. Tell everyone with an interest. Your bank, if the property is charged, and any registered lessee will be served and may share in the award. Talk to your bank early about how the redemption will be handled.
  8. Sort out estates and co-owners. If the registered owner has died, the family should start the estate process (letters of administration or probate) without delay. MRT Corp has already published notices tracing owners and next of kin.
  9. Don’t spend on improvements now. Additions made after the section 8 declaration, other than necessary repairs, are not compensated.
  10. Accept under protest if you disagree, and lodge Form N with full grounds within the deadline. Budget for the deposit of up to RM3,000.
  11. Plan the move. Ask when possession will be taken, and keep receipts for moving and re-establishing your business. Reasonable moving expenses are part of the compensation.
  12. If you are a landlord, check your tenancy agreement for what happens on compulsory acquisition, and give your tenant notice of what you know. See my guide to the Residential Tenancy Act and what it means for landlords and tenants.

Checklist: if you own property next to the route

  1. Find out what is planned next to you. Check whether a station entrance, viaduct, ventilation shaft or depot is planned nearby, using the scheme details from MRT Corp and DBKL or MPAJ.
  2. Expect construction years. Construction is expected from 2027. Plan for noise, dust, traffic diversions and access changes, and record the condition of your building before work starts in your area, with dated photos.
  3. Ask about the railway protection zone. Once the line is built, works near the railway structure, such as new developments, excavation, piling or the use of cranes, need approval under the Railways (Railway Protection Zone) Regulations 1998, with a no-objection letter from MRT Corp and approval from APAD. If you plan to rebuild or extend, ask early.
  4. If part of your land is taken, the value of the part you keep, and any severance or injurious affection, are part of the same claim. See the checklist above.

Checklist: before you buy near the alignment

  1. Ask the seller in writing whether the property, or any part of it, has received any acquisition notice (Form A, D, E, H or K), and get a title search before you sign.
  2. Check the title for a section 9 note of intended acquisition. If there is one, the price you pay will not raise the compensation. It is based on market value at the gazette date, and sales after that date are ignored.
  3. Don’t pay for a station that is not built. Station names and positions are provisional, and opening is targeted for 2032. Price the property on recent transactions of comparable units nearby.
  4. Check the walk, not the map. When the station is built, it is the walk to the entrance that matters. For now, a viaduct or shaft next door may matter more.
  5. Check title, tenure and land use. Freehold or leasehold, years left on the lease, any restriction on who can buy, and whether a high-rise unit’s strata title has been issued.
  6. Think about rental demand during construction. A unit next to a work site may be harder to let for some years. If you are buying to let, budget for that.
  7. For strata units, ask the management body whether it has received any notices about the line, and get the latest audited accounts and sinking fund figures. For older strata buildings, see my article on the Urban Renewal Bill and older strata properties in KL and Selangor.
  8. Budget for the full cost. Include stamp duty, legal fees and loan costs. See my guide to stamp duty self-assessment from 2027.

What to watch next

  • Progress against the end-2026 acquisition target, and any update on how many of the 690 lots have been awarded or taken over.
  • The section 8(4) dates: 15 July 2027 (Selangor) and 15 August 2027 (Kuala Lumpur), two years after the gazettes.
  • A main construction contract and an updated cost.
  • An official final station list from MRT Corp, and whether Stesen UM is confirmed.
  • Parliamentary replies. The July 2026 written reply was the most recent detailed official update I found.

What is still not confirmed

  • Final station names and positions. Only provisional names have been published.
  • The cost of the line. The last official target, from 2023, was below RM45 billion.
  • The construction contractor and start date. Construction is expected in 2027.
  • How much of the land has been acquired so far.
  • Any official measure of an “MRT3 premium” for property near the future stations. None exists.

Related reading

Sources

All read or re-checked on 4 November 2026.

About the author

Jessica Leong | Registered Estate Agent E3208
PropNex Realty Sdn Bhd (E (1) 1800/1), KLCC branch. Jessica covers new launch condos in Kuala Lumpur and Selangor, industrial property in Selangor, bank auction (lelong) properties, and Selangor offices, shophouses and en-bloc deals. See her new launch pages for Kuala Lumpur, KLCC, Petaling Jaya and Selangor.

PropNex Realty Sdn Bhd, A-G-03, Marc Residence, No. 3, Jalan Pinang, 50400 Kuala Lumpur
Office: 03-2161 8608 · Call/WhatsApp: 010-464 6088
Website: klselangorestates.com

This article is general information based on public sources as at 4 November 2026. It is not legal, tax, financial, valuation or investment advice. Station names are provisional, and project dates and figures may change. The summary of the Land Acquisition Act 1960 is simplified, and the Act has been amended; refer to the current text and get advice from your own lawyer and an independent registered valuer about your own lot. No official source measures a price premium for properties near the future MRT3 Circle Line.

WhatsApp JessicaEnquiry form

Own property in Kuala Lumpur and planning your next move?

If this article has you thinking about upgrading or your next purchase, send Jessica your details and she will reply by WhatsApp or phone. Prefer to chat now? WhatsApp 010-464 6088 or call.

* Required. Name and phone number are needed so Jessica can reply.

Written by Jessica Leong, Registered Estate Agent E3208, PropNex Realty Sdn Bhd E (1) 1800/1, A-G-03 Marc Residence, No. 3 Jalan Pinang, 50400 Kuala Lumpur, tel. 03-2161 8608. These articles are general information and market commentary, not financial, legal or tax advice; check the current facts with the relevant authorities and your own advisers before you act.